8.5 Business Cases and Expenditure Approval
| 8.5.1 | In approving any project, policy or programme, there should be an early opportunity for approving authorities to consider and influence the choices made. This could take the form of a formal submission of a SOC for approval or, on some occasions, informal contacts between the project sponsor and the approving authority. |
| 8.5.2 | Where expenditure proposals exceed the Department's delegated limits, DFP Supply will act as the approving authority. |
| 8.5.3 | For all major projects and high profile cases, Departments are required to submit a SOC to DFP Supply for approval in accordance with FD(DFP)12/11 before proceeding to develop an OBC. Relevant cases in this context are:
The £20m thresholds refer to costs expressed in real terms (i.e. in prices held constant at their current level), undiscounted. |
| 8.5.4 | OBCs must be formally submitted to DFP Supply for all investments over delegated limits, prior to the commitment of resources and commencement of procurement. |
| 8.5.5 | DFP approval of FBCs is currently required only for PPP/PFI cases. |